Skip to main content
Premier resource for practicing structural engineers
Go back to https://www.structuremag.org/articles Back
Article

Optimizing Module Dimensional Control in Energy Facilities

By Silky Wong, Ph.D, SE, PE, C.Eng, P.Eng. and Vigneshwar Natesan PE, P.Eng.
December 1, 2025

To view the figures and tables associated with this article, please refer to the flipbook above.

Dimensional control has emerged as a critical discipline in modular construction, particularly for energy infrastructure. The integration of dimensional control into early project phases ensures geometric fidelity—meaning that the construction of modules accurately matches the dimensions and spatial relationships as defined in the engineering model—across modules and mitigates risks associated with misalignment, settlement, and thermal expansion.

Dimensional control is a specialized form of surveying that focuses on precise measurements using techniques and methods designed to determine the three-dimensional spatial properties, dimensions, conformity, and interconnection of objects or structures through both simple and complex calculations. While it shares foundational principles with industrial metrology, dimensional control differs primarily in its broader scope and its application in more varied and often challenging field environments. As the design progresses, the Engineer of Record typically identifies the initial critical control points. These are then reviewed by the dimensional control surveying company. Upon client approval, the surveying company conducts the dimensional control survey and collects the necessary measurements to meet the module erection requirements.

Consequences of Late Mobilization of Dimensional Control Teams

The delayed engagement of dimensional control teams in modular construction projects can result in significant geometric discrepancies, misalignments, and costly rework. Dimensional control is not merely a verification step—it is a proactive quality assurance mechanism that should be embedded throughout the project lifecycle. Figure 1 shows an example of a misaligned pipe at the site when a dimensional control survey was not performed early during the fabrication at the module fabrication yard.

Loss of Geometric Fidelity

Without continuous oversight from dimensional control, control monuments and layout references are susceptible to settlement, thermal drift, and cumulative errors without being noticed. In one case, a project ran for 18 months with surveying lacking dimensional control requirements, resulting in misaligned bolt patterns across eight tank foundations. When the tank arrived, it could not align with the bolts. A dimensional control survey was subsequently conducted to enable trimming for fit-up. However, the tank holes were found to be deviated from the engineering design—an issue that early dimensional control verification at the fabrication yard could have identified and resolved.

Remote Fabrication Yard Challenges and Single Weld Hook-Up Strategy

Projects involving remote fabrication yards face compounded risks when dimensional control is not mobilized early. In a case involving a fabrication yard in the Gulf Coast region of the U.S., the absence of dimensional control jeopardized the single weld hook-up strategy. The mitigation involved leaving one module end long and performing as-built surveys post-installation to guide trimming of subsequent modules. This adaptive strategy enabled successful single weld hook-up execution across multiple modules, but only after dimensional control was engaged midstream.

Welding-Induced Deformation

Late dimensional control mobilization (Fig. 2) also limits the ability to influence fabrication procedures. On a project involving mega modules, pile caps were bowed up vertically in the middle (~0.236 inches dome) due to welding-induced shrinkage. The deformation disrupted the use of tapered shim plate, requiring grinding of the cap centerline to achieve surface-to-surface contact. Had dimensional control been present during early welding operations, procedural adjustments could have mitigated the bowing effects at the pile caps.

Field Fit-Up Challenges with Large-Diameter Piping

Large-diameter piping systems, typically those exceeding 30 inches in diameter, pose distinct challenges in modular construction, particularly within the energy facilities including liquefied natural gas. The following project cases collectively highlight the necessity of early and continuous dimensional control engagement in modular construction. From nozzle alignment to thermal expansion, proactive surveying and verification are essential to preventing costly errors and ensuring successful field fit-up of large-diameter piping systems.

Nozzle Misalignments, Error Amplification, and Spool Fit-Up

Nozzle misalignments and spool fit-up are common large-diameter piping installation issues, as they are highly sensitive to small coordinate deviations at source points like tanks, absorbers, and compressors. In a recent project, the absence of early dimensional control support for the compressor piping fit-up resulted in multiple failed spool installations and seven piping cuts. Facing the challenge of excessive spool shortening, dimensional control surveyors were finally brought in, and the surveyed data from spools and hard points were used to guide a single corrective cut. In another case, delayed surveying allowed minor misalignments to compound into nearly a foot of deviation after module placement, causing substantial cost and schedule impacts.

Thermal Expansion Considerations

Thermal expansion is another critical factor in large-diameter piping systems. Temperature differences between fabrication and installation environments can significantly affect pipe lengths due to the coefficient of thermal expansion in steel, potentially causing clashes or gaps. In a past project, modules fabricated in Louisiana (average temperature 69F) were installed in Alaska (average temperature 14F) without accounting for thermal differential. A large-diameter pipe designed for single weld hook-up spanning all modules (highlighted in red in Figure 3) led to repeated positional offsets, eventually deviating from the pile foundations’ centerline. Structural engineers halted further offsets due to integrity concerns, leaving a substantial gap between modules. Additional piping was procured to bridge the misalignment, delaying startup and triggering penalties from the State of Alaska. The cost impact, though unreported, was substantial. While observed thermal different effects may be misinterpreted as a design error, qualified dimensional control teams can mitigate this risk by establishing temperature correction protocols and adjusting the spool lengths accordingly, often using multiple target temperatures based on schedule and location. This example illustrates that dimensional control teams are not merely surveying control points but are also considering the broader project context to ensure successful completion of modular scope.

Pre-Delivery Verification

Dimensional control surveys conducted prior to taking ownership of structures and large diameter piping spools enable early detection of fabrication errors. In several cases, pre-fabricated spools were found to be dimensionally incorrect. Identifying these discrepancies in the shop environment prevents downstream installation issues and minimizes field modifications. Early verification not only improves installation efficiency but also enhances quality assurance across the project lifecycle.

Improving Structural QA/QC with 3D Surveying and Model Alignment Techniques

Although not traditionally categorized under dimensional control, modern structural QA/QC practices increasingly incorporate advanced surveying and visualization technologies to identify issues and verify tolerances. This is especially critical in large-scale modular construction projects, where conventional methods may be impractical due to access limitations or time constraints.

Laser Scanning to Validate Critical Tolerances at Tall Flare Tower

In one industrial facility, a tall flare tower was required to remain within a strict tolerance of ±50 mm. With limited access, 3D scanning proved to be effective in meeting this requirement. While laser scanning does not replace traditional dimensional control surveys, it enhances survey effectiveness by providing high-resolution spatial data.

3D Visualization for Tolerance Verification:
Tools like 3D heat maps (Fig. 4), inspection point clouds, and automated reports allow engineers to visually assess the conformance of fabricated or installed structures to design tolerances. These deliverables provide accurate visualizations of deviations, enabling quick detection of out-of-spec conditions and timely corrections.

Geo-Referenced Model Alignment
To maximize inspection accuracy, the design model, typically in .ifc format, is geo-referenced to the survey dataset using identifiable key connection points (such as bolt hole #1 at the base plate corner). This process begins with a full structure scan and simultaneous surveying of key locations. Aligning the model to these references eliminates control errors, instrument or setup inaccuracies, and ensures results reflect actual conditions.

Applications for Verticality and Tolerance Checks
By integrating high-precision instruments with intelligent model alignment workflows, teams can achieve more reliable QA/QC supporting both safety and performance goals, particularly for the following situations:

  • Verticality assessments of tall or complex structures.
  • Out-of-tolerance detection in prefabricated modules.
  • Surveying in remote or constrained environments.

Coordinated Interface Management with Dimensional Control for Preassembled Stack-up Modules

In this project, a structured interface management plan was established early among dimensional control teams, the owner’s construction group, precast manufacturer, structural steel fabricator, general mechanical contractor, and heavy-haul contractor to align expectations across stakeholders.

Design Provisions for Tolerance Control
During detailed design, provisions were incorporated to manage interface challenges. These included tighter tolerances for concrete pedestal pours with embedded anchor bolts and revised connection details (Fig. 5) at the top of precast columns to accommodate structural steel base plates. These measures helped reduce misalignment risks during construction.

Progressive Measurement and Verification
Critical interfaces, including anchor bolts in concrete pedestals, precast column bases, precast column-to-steel connections, and structural steel base plates (Fig. 6), were measured and checked for alignment by dimensional control survey team to provide unbiased data. Field measurements were continuously compared against design values, and any deviations were corrected before proceeding with the next installation step.

These proactive approaches prevented cumulative errors and significantly reduced the risk of costly rework during later phases.

Conclusion, Recommendations, and Moving Forward

The following dimensional control optimization framework is recommended to improve coordination, reduce rework, and prevent schedule delays:

Team Education for Establishing Full Dimensional Control Workflow: Promote awareness of dimensional control’s role in risk mitigation and encourage adherence to full workflows, from design and fabrication to field installation. Establishing appropriate fabrication tolerances and integrating dimensional control into QA/QC processes from the shop floor to the field further strengthens project delivery.

Early Mobilization: Engage dimensional control teams during initial layout and fabrication to monitor control points and minimize settlement-related alignment issues.

Design Provisions: Ensure engineering design supports dimensional control, for example, incorporate thermal expansion calculations into spool length specifications.

Pre-shipment Verification: Survey modules and spools at fabrication yards to ensure dimensional compliance before transport.

Field Monitoring: Integrate dimensional control into construction activities for alignment checks and corrections.

Advanced Surveying Tools: Where appropriate, utilize high precision surveying tools and scanning to improve measurement accuracy and data confidence.

As modular projects grow in complexity, adopting modern dimensional control practices is essential for improving precision and predictability in construction. Early deviation detection and strong stakeholder collaboration are key to minimizing risk and improving project outcomes. ■

About the Authors

Silky Wong leads the Civil, Structural & Buildings Modularization Technical Solutions team at Dow Inc. She chairs the ASCE Energy division task committee on Wind Induced Forces and serves on its Onshore Heavy Industrial Modularization Guidelines Task Committee.

Vigneshwar Natesan is currently pursuing a Master of Science degree in energy management from University of Texas at Dallas and is a member of the ASCE Energy division task committee on Wind Induced Forces. He was Civil Engineer Manager at Dow Inc. with over 13 years of industry experience.

References

  • ASCE (2024). Structural Design of Modules for Energy and Industrial Facilities. Reston, VA: American Society of Civil Engineers.
  • Wong, S., & McNeil, J. (2023). Using Dimensional Control to Mitigate Risk for Pre-assembled Units/Piperacks Installation. In: Proceedings of Structures Congress 2023, pp. 369–377.
  • Construction Institute (CII) (n.d.). Dimensional Control Strategies in Modular Construction [online video]. Available at: https://youtu.be/7MmlwQQrz1U?si=npTVdhtfLA-ui9E0 (Accessed: 12 September 2025).